RFP #2172

Shower Pan & Drain Installation + DOB Approval - NYC

Properties

...

409 E 84th St

Class

Commercial

Category

Office

Address

409 E 84th St, New York, New York 10028

RFP Scope

Mar 24, 2026 at 4:45 PM | Last updated

Description


Following GC demolition and shower preparation (Phase 1), a licensed NYC plumber is needed to supply and install a new vinyl shower pan liner and drain assembly, perform required flood testing, and coordinate the NYC Department of Buildings (DOB) inspection. This scope is Phase 2 and cannot begin until Phase 1 (GC demolition/prep) is certified complete.


Scope of Work


1. Pre-Mobilization

  • Confirm with property manager that GC demolition and subfloor preparation are complete before scheduling mobilization.
  • Coordinate site access with building management.


2. Shower Pan Installation

  • Inspect the exposed shower area upon arrival to verify the floor is suitable for installation.
  • Supply and install one (1) new vinyl shower pan liner.
  • Supply and install a new shower drain assembly.
  • Reconnect drain assembly to existing drain piping, ensuring all connections are properly secured and leak-free.


3. Testing & DOB Inspection

  • Perform initial functional test of the drain connection upon installation.
  • Fill the shower pan with water and conduct a 24-hour flood test to confirm watertight integrity.
  • Schedule and call for the required NYC DOB inspection upon successful flood test completion.


4. Post-Inspection Finish Work

  • Following DOB inspection approval, the GENERAL CONTRACTOR will complete:
  • Tile installation (floor and walls)
  • Shower curb reconstruction
  • Closing and finishing all wall and floor openings


Deliverables


  • Installed and tested vinyl shower pan liner and drain assembly.
  • Documented 24-hour flood test results.
  • Completed DOB inspection with approval.

Dealbreakers


Vendor requirements


NYC Licensed Master Plumber

$1M Commercial General Liability Insurance

$1M Workers' Compensation Insurance

DOB inspection scheduling experience

Book a site visit

Instructions


Select a date

Select a time

Select a date to see available time slots

Posted by

...

Brian Kay

Property and Construction Manager at Choice new york

Project overview

Work categories

Plumbers

Bidding deadline

Apr 4, 2026

Work dates

Apr 6, 2026 - Apr 10, 2026

Budget

No budget

Light RFP Fee
2% of the winning bid.

Need help?

Darryl A.

Senior SDR at Light RFP

Call Email

About Light RFP

Procurement perfected.

Discover RFPs, attend site visits, ask RFIs, submit bids, and win new business with Light RFP's procurement platform.

Find the best projects for your business.

Receive invitations to RFPs or search through Light RFP's marketplace of live RFPs to bid on available projects in your area.

Only pay for contracts you've won, not leads.

2% of the winning bid is charged immediately upon contract signing. You pay nothing if your bid is not selected.

Centralize compliance requirements for quick bidding.

All COI, W9, insurance policies, and certifications are stored in the platform to keep your data organized, up to date, and ready to bid.

Request for information

Anonymous RFIs

Post a question here and it will appear anonymous to the public. The property manager will still be able to know who you are in order to best answer your question.

Ask an anonymous question

Looking for more projects?

Browse available RFPs on our marketplace.